From Contract to Cooking: Our 8-Step Kitchen Remodel Timeline – What to Expect, Week-by-Week

Setting the Clock

One of the most frequent questions we get is, “How long will I be without a kitchen?” I get it—your kitchen is the heart of your home. As your contractor, my job is to manage the chaos and provide a reliable timeline. A typical, full kitchen renovation (Mid-Range Upgrade) takes between 8 to 12 weeks of construction time, but the preparation is just as important. Here is the step-by-step process we follow to ensure your project stays on track.

Phase 1: The Prep Work (Weeks 1-2)

  • Step 1: Demo Day & Prep: We secure the site, protect the rest of your home, and completely gut the old kitchen. This is the loud, dusty part that moves fast!

  • Step 2: Rough-In Inspections: The bones of your new kitchen are laid out. Our plumbers and electricians install new lines, often while the walls are still open. We get the necessary rough-in inspections done quickly to avoid delays.

Phase 2: Building the Core (Weeks 3-5)

  • Step 3: Close-Up & Finishing: Walls are closed, drywall is installed, taped, and mudded. We move on to painting. This is when the room starts to feel like a space again, not a construction site.

  • Step 4: Flooring Installation: A critical milestone. Whether it’s tile, hardwood, or LVP, the floor is installed to create a clean base for the cabinetry.

Phase 3: The Big Reveals (Weeks 6-10)

  • Step 5: Cabinet Installation: This is the most rewarding part for the homeowner! Cabinets are set, leveled, and secured. The room’s function is defined.

  • Step 6: Countertop Templating & Installation: Once cabinets are in, we precisely template for your countertops. This step has a mandatory 1-2 week lead time for fabrication. Once they arrive, installation is quick and transformative.

  • Step 7: Final Plumbing & Electrical (The Trim Out): Sinks, faucets, lighting fixtures, outlets, and switches are installed. Your appliances are moved in and hooked up.

Phase 4: The Finish Line (Weeks 11-12)

  • Step 8: Punch List & Final Inspection: We walk through the space with you to address any minor details (“the punch list”). The final inspection is scheduled and passed. You get your kitchen back!

Our Contractor Promise

A remodel is a journey. We manage the logistics—ordering, scheduling, and inspections—so you can focus on the final look. Our commitment is to clear communication at every step. Ready to see our detailed project plan for your home?